prEN 12699 rev

Execution of special geotechnical works - Displacement piles prEN 12699 rev

General information

10.99   New project approved   Sep 22, 2026

CEN

CEN/TC 288 Execution of special geotechnical works

European Norm

Scope

This document establishes general principles for the execution of displacement piles, that means piles which are installed in the ground without excavation or removal of material from the ground except for limiting heave and/or limiting vibration as well as removal of obstructions or to assist penetration.

Displacement piles are driven into the ground using impact, vibration, pressing, screwing or a combination of these methods.

NOTE 1: If a closed end drive tube with d < 300 mm is removed and a solid bar as a load bearing element is used, the execution is covered by EN 14199 for corrosion considerations.

The material of displacement piles covered by this European Standard can be:
- steel;
- cast iron;
- concrete, mortar;
- timber;
- grout;
- combination of above.

This document covers prefabricated, cast in situ, or a combination of these methods to form displacement piles of regular shape. The pile types are listed in EN 1997-3, annex C.3, table C.1.

NOTE 2: Partial displacement piles executed with a drive tube with a limited number of helices at its base are covered in the following standard.

NOTE 3: Partial displacement piles installed with a drive tube with helices along the whole length are executed by EN 1536.


Displacement piles may be installed in soils enhanced by ground improvement techniques. The ground improvement can be executed before, at the same time or after installation of the piles.

Other than practical considerations there are for the purpose of this European Standard no limitations regarding cross section dimensions, shaft or base enlargements, length or rake.

The provisions of this European Standard apply to:
- single piles;
- pile groups;
- concrete sheet piles.

Columns constructed by ground improvement techniques (such as mixed in situ columns, jet grouting, compaction grouting, vibro flotation, stone columns) are not covered by this European Standard. Bored piles are covered in EN 1536. Steel and timber sheet pile walls are covered in EN 12063. Micropiles are covered in EN 14199.

Life cycle

PREVIOUSLY

PUBLISHED
EN 12699:2015

NOW

IN_DEVELOPMENT
prEN 12699 rev
10.99 New project approved
Sep 22, 2026




Access Genorma App Everywhere

Get fast and easy access to top European and International standards (EN, ISO, IEC) via your mobile phone, tablet or the web.